Renovations Diary

15th March 2019

On Wednesday, students from The Green Room School visited The Swan. They pitched in and removed the planters from the side door and took the soil to the local allotments. They also helped Jeff the plumber remove the toilet and wash basin from the large hall – this will become the school/function room.

As you may have guessed, the strong winds and general weather conditions have slowed things down a bit this week. That said, Peter, Matt and Ian have been making amazing progress replacing the roof of the laundry and also the men’s toilet too. Both have had all the timberwork replaced and the actual roof itself fibre-glassed. This has saved us a considerable amount of money by doing the work in-house.

Now that we have those in place, Warren came back on Friday to add more scaffolding to that area. We still await clearance to bridge over the electric sub-station behind The Swan. Hopefully, that will come soon. Don’t get worried over the weekend if you see men on the main roof. The roofing team are working this weekend. They will be inspecting the roof and starting the necessary repairs. It’s only now that we have better access that we can fully understand what is required.

We got a bit of a surprise in the corridor that leads up to the main hall. We were going to repair the wood panels that had been damaged. However, once we removed it, you can see why we had to keep going.