Renovations Diary

3rd July 2020

The Coach House

The Jayflex team have continued to make great progress on making The Coach House a safe and exciting venue for use by both Green Room School and Swan activities. We are very lucky to be able to benefit from their skill and generosity.

The lintel over The Coach House doors was replaced with steel.

The guys have been ploughing on with the brickwork and have got it ready for the lintel to be put in place.

The steels were delivered, but unfortunately the lorry with the crane could not get into The Courtyard, so the final placement was delayed to the 4th.

Weekday Warriors

At the same time, our Weekday Warrior volunteers have been equally hard at work helping to get the place ready for re-opening on Saturday.