14th May 2021
Another busy week for the Weekday Warriors as well as Shane & Dale. The Warriors have carried on inside The School Room, reinstating the flooring, restoring wall panelling and framing in a faux chimney breast to restore the fireplace. They then worked around the extract riser up to the roof where Shane and Dale were finishing the slating-in and weatherproofing up top. If that wasn’t enough, they moved to cover a hole in a corner of The School Room roof where it had previously been necessary to remove the top part of a fragile chimney. Before the weather turned, Shane and Dale were back on The Stables roof dealing with problems along the back section.