Renovations Diary

10th September 2021

The Warriors have been hard at it again this week. The fire boarding of The Kitchen ceiling is now complete. Next week work will start on fitting the battens and boarding to the walls in readiness for plastering. To minimise disruption to GR6 pupils the Warriors also found time to install trunking for the power cables in The Stables.

Meanwhile in the pub itself, Micky was putting in a bookcase which will be stocked up in the very near future.