2nd April 2021
The results of the air conditioning installation are visible … for a short time only. The schoolroom will be reinstated for the new term starting, and below, the ceiling completed and made for the sparkies and then plasterboarding.



The guys have been busy in The Kitchen and hallway too. The armoured cable protectors have been laid and the next layer of The Kitchen floor laid and tamped down.




And yet another delivery. This time it is for sand that will be used in the concrete for The Kitchen floor. The guys are now on a tight timetable as this must be cleared before re-opening on the 12th. Good luck!




And there were further deliveries too. The new stairs have been made and delivered, ready for installation in a couple of weeks. Also a lot of timber that is going to be required for The Kitchen, hallway and The Storeroom. Unfortunately, the lads had to hire a van and pick this up ourselves, costing valuable time and cash.