28th January 2022
It has been an extremely busy seven days for the team. They were in last week to ensure that the Thursday deadline for commissioning of the equipment was achieved. This they did and in style. Just see the progress this week …
Windows
After fitting the first window last week, the second one was installed this week. The exterior security covering had to be cut back, and then the whole frame sorted out. Only then could the window actually be installed. That leaves one more when the window actually arrives.




Tiling
Another part of this week was to start the tiling and have at least the minimum required so that the sink and other units could be tested for position. In the end, the while kitchen will either be stainless steel or tiles, but for now, this was enough for the commissioning activities. You can see what the guys will be doing for the next week.



Moving the Equipment In
There was quite a lot of equipment to be moved into place before McFarlane Telfer could commission it. All of it is heavy, all of it is awkward, and all of it is stainless steel in appearance. So it was handled with care as it was moved through the various doors and the corridor to its final position.








Lighting
Keith, our electrician, finished off the various lights in The Kitchen. Those underneath the hood and the wider ones covering the whole kitchen area. To say they are very bright is an understatement! No one will have the excuse that they didn’t see something because it was dark.




McFarlane Telfer
The equipment is to be installed and commissioned by McFarlane Telfer, who has been a great supporter of our Kitchen Project. We can’t thank them enough for what they have done for us and what they have donated. The pizza oven, now in situ, is a fine example. They will be back in a couple of days to finish it all off. The equipment is now under wraps, so it doesn’t get dirty.





We have come so far in recent weeks as it all comes together. We have a small glimpse of what is to come when the tiling is completed – the sink and other equipment were put in place temporarily to check the fit. Looks good! And under all those sheets is a kitchen trying to burst into life!
Store Room
The Store Room took big steps forward, too. The back wall was finished with the various layers of board. Ian the Plasterer then came in, and when the plaster was dry, it was misted and given a first coat. There is still a lot to be done in here before the racking goes in.




Cold Room
And finally, the ceiling in The Cold Room was completed. This required a little remedial work on the timbers before being insulated and covered with fireboard. The rest of the room was finished off, cleared out and is now ready for plastering and tiling.