25th November 2022

Building work has continued despite the heavy rain this last fortnight. Paul the roofer finished repairs to the top accessible parts of the roof.

This meant we were ready for the top parts of the scaffold to come down! Yes, that’s right, if you passed by The Swan yesterday, you would have seen Warren disassembling and lowering the two upper platforms of the scaffold, ready for Paul to move to the next part of the roof work.

Meanwhile, Tex and Sam, the painters, have been prepping and painting the windows on the side and rear of the building. More work will progress next week, with plans to remove the scaffold in sections as the work is completed, so watch this space!