Renovations Diary

6th September 2019

Probably the biggest news of this week is that the scaffolding has started to come down. Okay, it is only a small bit, but it is a start. This was around the entrance to the school room. Also, the iron railings were welded back on after making some small repairs.

And the sparkies have been hard at it this week, connecting up the cellar, the bar, the toilets and the school room. They have a little work to do behind the scenes to connect up the boiler and heating, but they are ready for the fire and security equipment to be connected up tomorrow. In a couple of weeks, they will set up the wifi.

The team have also been busy putting fire doors on the toilets, varnishing the school room floor, further stripping of the front windows, plasterboarding in the hall, and working to commission the gents toilet (very soon, guys, honest).