Renovations Diary

1st November 2019

Due to excessive rain, we had some issues with leaks in the main building. The priority, therefore, became doing quick repairs and then accelerating the replacement of the soffits, fascias, and guttering. Also, some of the broken and missing tiles need to be replaced.

In preparation for the contents of the stables moving into the main building (due to some events in December), the floor boards were replaced, and the floor was made good. A lot of reorganisation of the contents was done to allow more to be added.

We also started the tidy-up of the office so that the next steps can take place.